Slater Street - Road reconstruction, including road narrowing and new street tree planting

Submissions: Phone us: 941 8999, 8am-6pm
Contact: Tara King
Phone: 941 5938, 027 208 3235

Affects

Areas affected:
Wards affected: Papanui, Shirley
People affected: General community

Timeframe

Open date: 16/10/2015
Close date: 02/11/2015 5:00p.m.

Links

Project information: View the project information page
Map:
Project website:
Consultation website:
Other links -
(Project):
Public Information Leaflet
Submission Form
Feedback to Submitters - Slater Street
Other links -
(Consultation):

Full description

What and Why
As part of the ongoing earthquake repair works, the Stronger Christchurch Infrastructure Rebuild Team(SCIRT) will be undertaking final road reconstruction works on Slater Street. These works will involve a new layout in a small section of Slater Street - (between Dudley Street and 71/78 Slater Street). The remaining sections of Slater Street will have minor repairs carried out and will be left in the original road layout. SCIRT is only delivering a limited number of streets where full reconstruction is required. For Slater Street, the worst affected area will be fully reconstructed. The remaining area will go into the Council future maintenance programme.
The new road layout will involve new kerb and channel that will be constructed on the road side of the new street trees. This will reduce this section of Slater Street to a 9 metre kerb to kerb roadway, which is standard width for a local residential road. The new layout will balance the need for parking on both sides of the street and still allow for two way traffic flow.
All street trees within the road narrowing area (refer locality plan) will be removed and replaced with Trident Maple (Acer Buergerianum), and new grass berms installed. With the kerb now being on the road side of the trees, this will allow for better maintenance and protection of the street trees and grass verges.

Features of this proposal (refer plan)

  • Kerb to kerb road reconstruction, with new kerb and channel in narrowed areas.
  • New road layout (road narrowing) with the kerb and channel being on the road side of the street trees, and new grass berms.
  • Existing street trees (at the intersection of Dudley Street and Slater Street) removed due to upcoming construction works. New street trees will be planted on Slater Street.
  • New no stopping lines at localised road narrowing points, ie intersections.

    Timeline
    16 October 2015 - Consultation opens

    2 November 2015 - Consultation closes

    16 December 2015 - Shirley/Papanui Community Board meeting to approve road layout changes

    January 2016 - SCIRT works to commence

    September 2016 - SCIRT works to complete